# GCA-1 — DISMISSED ON ARRIVAL: "the December gate's day count disagrees across three records" — the arithmetic does not reproduce, and the proposed fix would have put the error INTO the record it was protecting

status: dismissed · raised AND killed in panel run 50 (2026-11-16) · class:
**would-be P1 registration** · never filed as open

---

**What was claimed.** That `thales go-live-gate`'s 108 live trading days
projected forward gave **118 on 2026-12-01 · 125 on 12-10 · 126 on 12-11**,
and that therefore `AUDIT.md:128`'s fire-once register row ("reaches **119 on
2026-12-01** and **126 on ~2026-12-10**") was off by one, as was
`research/steward/2026-11-12.md`'s carried-forward line.

**Why it is wrong.** The count's anchor was misread. `thales go-live-gate`
prints "108 … as of 2026-11-16", but `data/processed/equity_history.jsonl`'s
last row is **2026-11-13** — today's box run fires at 15:35Z and has written
nothing. So 108 counts **through 11-13**, and 2026-11-16 itself is an
uncounted trading day. Both the queue-and-clocks lens and the panel chair
walked forward from 11-17 and dropped it.

Counting 11-16 onward inclusive (`thales.utils.calendar.is_trading_day`;
2026-11-26 Thanksgiving confirmed a non-trading day):

| date | n_live |
|---|---|
| 2026-11-16 | 109 |
| **2026-12-01** | **119** |
| **2026-12-10** | **126** ← first day ≥ 126 |
| 2026-12-11 | 127 |

**`AUDIT.md:128` is CORRECT.** Independently corroborated: `AUDIT.md:247`'s
2026-11-01 weekly-audit entry derives the same 119 / 12-10 from a 98-day read,
and 98 + the ten trading days 11-02…11-13 = 108, so no days were lost and two
derivations three weeks apart agree.

**Why this kill is worth recording rather than quietly dropping.** The
register row exists precisely so that *"a NOT-PASS driven purely by
`min_live_trading_days` is never quoted as a forward-performance result."* The
proposed remedy would have **written a one-day error into that row** — a
finding whose fix degrades its own target. It was also a **correlated error**:
the lens made it and the chair reproduced it with the same loop before
catching it, and the adversarial reviewer derived the correction independently.

**The one true residue, handled as a carry-forward, not a row.**
`research/steward/2026-11-12.md:35` reads *"**12-10:** the earliest date the
December gate can be decided (**107/126 that day**)"*. The 107 is that run's
own as-of count mislabelled as 12-10's; the correct figure is 126/126. The
sentence's headline ("12-10 is the earliest date") is right and agrees with
AUDIT.md, so the parenthetical contradicts its own clause and reads as a typo.
Carried to the 2026-11-19 steward run in panel run 50's report and beacon
marker.

## Reopen conditions (any one)

1. **The gate's day count is quoted in a decision record as a
   forward-performance result without its day count alongside it.** That is
   `AUDIT.md:128`'s own pass criterion, still ⏳ pending, and it is the thing
   this candidate was reaching for.
2. **`go-live-gate`'s `min_live_trading_days` basis changes** (marks vs
   returns, or the clean-clock `since` moves) **without the register row being
   re-derived** — at which point three records would genuinely diverge rather
   than one carrying a typo.
3. **A trading day is actually lost** (an outage with no equity row) between
   now and 2026-12-10, which pushes the 126th day later than the register row
   projects. The row already caveats this ("assuming no missed days — any
   outage pushes it later"), so the reopen is for the case where the caveat
   fires and nobody updates the date.